Dry Docks World boring precision and response drive follow on work

New build Jack up crane barge machining

As part of the recently signed agreement between Goltens and Dubai Dry Dock, Goltens was engaged to perform In-situ machining/boring of locking pin guides for a new build jack up crane barge. The job was line boring of two bushes that would act as locking pin bores to support jacking legs when in service.

Goltens mobilized tools and technicians to the dry dock the day the initial inquiry was received and the machining was started the following morning. The project was to be completed on an urgent basis. Dubai Dry Docks had a total of 24 bores to be completed and had engaged two additional firms to work in parallel with Goltens on other surfaces

Goltens Dubai technicians outperformed the other contractors with their tooling to such an extent that Goltens was asked to engage an additional boring machine and additional in-situ teams so that both machines could be utilized around the clock.

With two machines working 24 hours a day and two teams working simultaneously Dubai Dry Docks made the decision to give the entire job to Goltens and the other firms disengaged.

  • Boring equipment set up inside jacking leg column - Annealing Journal Machining

    Boring equipment set up inside jacking leg column - Annealing Journal Machining

  • References marked off for machining

    References marked off for machining

  • Machining of locking pin bore

    Machining of locking pin bore

PROJECT FACTS

Line Boring of Jack up Crane
Original Bore Diameter: 217mm
Final Bore Diameter: 227mm
Number of Bores completed: 12

REPAIRS

  • In-Situ line boring of 12 locking pin bores.

RESULTS

The initial project scope was for Goltens to complete 6 locking pin bores but was further engaged to complete the 6 remaining bores as a result of the quality and speed of the services provided. “…I want to express our gratitude and great satisfaction for the excellent job done by your Site Team, you assisted us in the best possible way, when we needed your best performance we got it.” -Svetozar Milosevic Estimator Drydocks World-Dubai.

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/dry-docks-world-boring-precision
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=dry-docks-world-boring-precision&page=
Loaded Template: single-resources.php
Search Goltens ×