be_ixf;ym_202404 d_19; ct_50

Turnkey Retrofit for EGCS SOX Scrubber & BWTS

QUICK RESPONSE AND FOCUSED EXECUTION ENABLE LPG OPERATOR TO MEET EMISSIONS AND BALLAST WATER COMPLIANCE

A prominent LPG Tanker owner engaged Goltens Green Technologies division in Singapore to undertake a turnkey project for the simultaneous installation of an exhaust gas cleaning system/Sox Scrubber (EGCS) and a Ballast Water Treatment System (BWTS) to comply the IMO regulations.

The shipowner planned ahead and commenced the project 6 months before the planned docking at a Chinese shipyard. The time allotted allowed for a smooth and highly collaborative engineering process and successful completion of this complex multi-system project.

SCOPE OF WORK:

  • 3D scanning & vessel survey
  • Basic and detailed engineering
  • Class approvals & Shipyard Management
  • Procurement & Prefabrication
  • Turnkey Project Management
  • Installation supervision
  • Kwang Sung Open Loop scrubber casing integration

    New Scrubber casing integration

  • Exhaust funnel before scrubber installation

    Old funnel (pre-Scrubber installation)

  • Kwang Sung Open Loop scrubber installed with extended funnel

    Extended funnel with scrubber installed

  • 3D model of Kwang Sung Open Loop scrubber system

    3D scrubber model overlaid on 3D scan data

  • 3D Model of Kwang Sung Open Loop scrubber design

    3D ISO view of Scrubber system

  • Alfa Laval bwts modeled over 3D scan data

    BWTS modelled over 3D scan data

  • Alfa Laval BWTS Unit installed in Engine Room

    BWTS Unit installed in Engine Room

  • 3D model of Kwang Sung Open Loop scrubber GRE discharge piping

    3D model of GRE Scrubber Discharge Line

  • Kwang Sung Open Loop Scrubber GRE discharge line

    GRE Scrubber discharge line installed

  • Kwang Sung Open Loop scrubber seawater pump model

    3D Model of SW Pumps for Scrubber Feeder Line

  • Kwang Sung Open Loop scrubber seawater pumps installed

    SW pumps for Scrubber Feeder Line installed

  • Retrofit Project schedule

  • Goltens' and shipyard scrubber retrofit team

    Goltens & Shipyard team after successful install

DESIGN & ENGINEERING:

Goltens’ retrofit survey team undertook the onboard survey and 3D laser scanning in less than 4 days. From the outset, the primary constraint of the scrubber part of the project was the limited size of the existing funnel, and the physical size and configuration of the U-Type venturi scrubber chosen. A major extension to the funnel was identified by all parties as the only viable option.

Goltens’ design engineering team, working closely with Kwang Sung and the vessel owner, identified the most efficient approach to minimize the extent of the required extension. The innovative design delivered managed to retain a somewhat streamlined and aesthetically pleasing “backpack” arrangement.

Given the compact engine room and lack of free space on the engine floor level, locating the Scrubber SW supply pumps, associated equipment and ECU units for the BWTS was also a challenge.

Production design & class approval were completed efficiently, topping off a successful retrofit design project that took 4,700 manhours from contract award to delivery of production design drawings.

INSTALLATION PHASE: 12,500 MANHOURS/29 DAYS

Goltens’ deployed three highly experienced engineers to supervise structural, piping and electrical disciplines at the Chinese shipyard. Over the course of the next 29 days, Goltens successfully managed site supervision of 12,500 manhours applied to shipyard jobs for the BWTS and Scrubber retrofits.

PROJECT SUCCESS RESULTS IN FOLLOW ON WORK:

Goltens worked closely with the owners to avoid any delays to schedules which came from technical obstacles encountered and delivered the project ahead of schedule.

As a result of the successful completion of the job, the owner decided to award three follow on Scrubber/BWTS retrofit projects to Goltens. Another validation point for Goltens’ well tested and well executed retrofit process.

TECHNICAL DESCRIPTIONS:

Vessel Length (LOA)

225.28 m

Vessel DWT

82.000

Built Year &Yard

2009 – DSME, Korea

Gross Tonnage

47,276

Main Engine

B&W 6S60MC-C

Max Engine Power

13,560 kW

Aux Engines (3Nos)

Hyundai 8H21/32

Aux Engine Power

1280 kW

BWTS

Alfa Laval PureBallast 3.1- 750 (2 sets)

Ballast Pump

800 m3/h x 2 sets

Scrubber Type

Kwang Sung Open Loop

Scrubber Dimension (m)

7.05L x 4.0D x 10.55H

Max. Design Exhaust gas flow

137,709 (kg/hr)

SO2 Compliance Level

0.5 % Non-ECA

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/turnkey-retrofit-for-egcs-sox-scrubber-bwts
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=turnkey-retrofit-for-egcs-sox-scrubber-bwts&page=
Loaded Template: single-resources.php
Search Goltens ×