Engineering and Installation of Expanded Cooling Water System for New Crane Retrofit

SHIPYARD INSTALLATION IN 16 DAYS

A vessel operator, familiar with Goltens’ ballast water treatment system (BWTS) retrofit capabilities, approached Goltens to engineer and install modifications to an existing vessel cooling water system to accommodate a replacement crane.

The project required the integration of new seawater (SW) and freshwater (FW) cooling systems, including additional pumps and a heat exchanger, within the vessel’s existing infrastructure. With installation scheduled during a planned dry-docking, efficient engineering, prefabrication, and execution were essential to meeting the vessel’s operational schedule.

INTEGRATED ENGINEERING, PROCUREMENT & INSTALLATION SERVICES

Using 3D scanning data collected onboard in Brazil, Goltens developed a concept design for the expanded cooling water arrangement, including the selection of a new heat exchanger and pumps and the design of the required SW and FW cooling systems.

Following customer approval, Goltens completed the detailed engineering package covering equipment specifications, piping arrangements, material requirements, and installation documentation.

Goltens subsequently secured the contract for equipment and material supply, piping prefabrication, and mechanical and electrical installation.

Procurement and prefabrication were coordinated in advance of the vessel’s scheduled dry-docking to minimize onboard installation time. Once materials and equipment arrived at the shipyard, Goltens mobilized its mechanical and electrical teams to execute the retrofit under dedicated project supervision, maintaining daily progress communication with the customer.

  • Detailed engineering model of F/W cooling system

    Detailed engineering model of F_W cooling system

  • Engineering model of S/W cooling system

    Engineering model of S_W cooling system

  • Existing layout prior to F/W cooling system

    Existing layout prior to F_W cooling system

  • Space prior to expanded S/W cooling system

    Space prior to expanded S_W cooling system

  • S/W cooling system installed according to design

    SW cooling system installed according to design

  • F/W Cooling system installed

    FW cooling system installed

SCOPE OF WORK

  • 3D scan-based concept and detailed engineering
  • Cooling system design and equipment specification
  • Project management and procurement
  • Piping prefabrication and material supply
  • Mechanical and electrical installation
  • Testing, commissioning, and handover

THE RESULTS – INSTALLATION IN 16 DAYS

Goltens successfully completed the installation and commissioning of the new seawater and freshwater cooling systems in 16 days during the vessel’s scheduled dry-docking.

The new systems were fully integrated with the existing vessel infrastructure, tested, and handed over ready for operation.

Through coordinated engineering, advance prefabrication, and efficient onboard execution, Goltens delivered a complete retrofit solution within the customer’s planned maintenance window, minimizing disruption to the vessel’s operational schedule.
 

Download a PDF of this Resource

(Right click and select "Save File As..." or "Save Link As..." to save)

Download Now
Dev Tool:

Request: resources/engineering-and-installation-of-expanded-cooling-water-system-for-new-crane-retrofit
Matched Rewrite Rule: resources/([^/]+)(?:/([0-9]+))?/?$
Matched Rewrite Query: resources=engineering-and-installation-of-expanded-cooling-water-system-for-new-crane-retrofit&page=
Loaded Template: single-resources.php
Search Goltens ×