Engineering and Installation of Expanded Cooling Water System for New Crane Retrofit
SHIPYARD INSTALLATION IN 16 DAYS
A vessel operator, familiar with Goltens’ ballast water treatment system (BWTS) retrofit capabilities, approached Goltens to engineer and install modifications to an existing vessel cooling water system to accommodate a replacement crane.
The project required the integration of new seawater (SW) and freshwater (FW) cooling systems, including additional pumps and a heat exchanger, within the vessel’s existing infrastructure. With installation scheduled during a planned dry-docking, efficient engineering, prefabrication, and execution were essential to meeting the vessel’s operational schedule.
INTEGRATED ENGINEERING, PROCUREMENT & INSTALLATION SERVICES
Using 3D scanning data collected onboard in Brazil, Goltens developed a concept design for the expanded cooling water arrangement, including the selection of a new heat exchanger and pumps and the design of the required SW and FW cooling systems.
Following customer approval, Goltens completed the detailed engineering package covering equipment specifications, piping arrangements, material requirements, and installation documentation.
Goltens subsequently secured the contract for equipment and material supply, piping prefabrication, and mechanical and electrical installation.
Procurement and prefabrication were coordinated in advance of the vessel’s scheduled dry-docking to minimize onboard installation time. Once materials and equipment arrived at the shipyard, Goltens mobilized its mechanical and electrical teams to execute the retrofit under dedicated project supervision, maintaining daily progress communication with the customer.
SCOPE OF WORK
- 3D scan-based concept and detailed engineering
- Cooling system design and equipment specification
- Project management and procurement
- Piping prefabrication and material supply
- Mechanical and electrical installation
- Testing, commissioning, and handover
THE RESULTS – INSTALLATION IN 16 DAYS
Goltens successfully completed the installation and commissioning of the new seawater and freshwater cooling systems in 16 days during the vessel’s scheduled dry-docking.
The new systems were fully integrated with the existing vessel infrastructure, tested, and handed over ready for operation.
Through coordinated engineering, advance prefabrication, and efficient onboard execution, Goltens delivered a complete retrofit solution within the customer’s planned maintenance window, minimizing disruption to the vessel’s operational schedule.
Download a PDF of this Resource
(Right click and select "Save File As..." or "Save Link As..." to save)
Download Now




